TxDOT San Angelo district lettings
107 lettings in the current 24-month TxDOT window; 86 have an apparent low bid. Latest let date: 2026-11-19. Showing the 60 most recent.
| Let date | CCSJ | County | Highway | Work | Bidders | Apparent low bidder | Low total | Sealed est. | Low ÷ est. |
|---|---|---|---|---|---|---|---|---|---|
| 2026-11-19 | 6512-46-001 | Kimble | US0377 | TREE TRIMMING AND BRUSH REMOVAL | 8 | ALLIES LAND CLEARING | $159,400 | $202,250 | 78.8% |
| 2026-11-10 | 6512-41-001 | Tom Green | SH0208 | STATE USE CONTRACT | 0 | – | – | $41,281 | – |
| 2026-11-10 | 6512-40-001 | Tom Green | RM0584 | STATE USE CONTRACT | 0 | – | – | $97,943 | – |
| 2026-11-04 | 6504-98-001 | Tom Green | SH0208 | ASPHALT PAVEMENT REPAIR | 4 | REECE ALBERT, INC. | $3,124,443 | $1,794,178 | 174.1% |
| 2026-10-07 | 0907-00-217 | Tom Green | Various | Highway Improvement | 7 | FLAT LINE, INC. | $2,539,432 | $3,446,187 | 73.7% |
| 2026-10-01 | 6502-82-001 | Tom Green | SH0208 | CRACK SEAL | 6 | D & M CONTRACTORS, LLC | $731,323 | $882,416 | 82.9% |
| 2026-09-29 | 6508-59-001 | Kimble | FM 2169 | CULVERT REPAIR | 5 | MPB, INC. | $229,995 | $428,414 | 53.7% |
| 2026-09-17 | 6508-58-001 | Tom Green | SH0208 | MOWING HIGHWAY RIGHT OF WAY | 5 | ABESCAPE LANDSCAPING, LLC | $202,188 | $210,560 | 96.0% |
| 2026-09-15 | 6508-57-001 | Tom Green | SH0208 | MOWING HIGHWAY RIGHT OF WAY | 5 | Diamond Rack Ranch LLC | $261,492 | $308,175 | 84.9% |
| 2026-09-10 | 6501-04-001 | Kimble | US0377 | BRIDGE PREVENTATIVE MAINTENANCE | 10 | 12TWELVE ROAD AND BRIDGE LLC | $449,985 | $533,850 | 84.3% |
| 2026-09-08 | 6508-40-001 | Tom Green | US0067 | LIMESTONE ROCK ASPHALT | 2 | VULCAN CONSTRUCTION MATERIALS, LLC | $341,356 | $373,411 | 91.4% |
| 2026-09-08 | 6508-22-001 | Tom Green | RM0584 | PAINT AND BEADS | 3 | DIGG COMMERCIAL, LLC | $390,154 | $372,480 | 104.7% |
| 2026-09-03 | 6501-05-001 | Tom Green | SH0208 | BRIDGE PREVENTATIVE MAINTENANCE | 11 | THE TRUESDELL CORPORATION | $1,383,383 | $1,329,347 | 104.1% |
| 2026-09-01 | 6504-86-001 | Tom Green | US0067 | WINTER WEATHER MATERIAL | 3 | TOUCHSTONE RESOURCES, LLC | $90,000 | $87,120 | 103.3% |
| 2026-09-01 | 6504-85-001 | Reagan | US0067 | WINTER WEATHER MATERIAL | 3 | DESERT LUXURY TRANSPORTATION, LLC | $285,600 | $216,000 | 132.2% |
| 2026-09-01 | 6504-84-001 | Tom Green | US0087 | WINTER WEATHER MATERIAL | 3 | CLEMENTS FLUIDS SOUTH TEXAS, LTD. | $462,649 | $537,511 | 86.1% |
| 2026-08-18 | 6503-18-001 | Tom Green | SH0208 | CLEANING AND SWEEPING HIGHWAYS | 4 | SUNDROP GARDENS LANDSCAPING, LLC | $490,191 | $563,316 | 87.0% |
| 2026-08-06 | 0140-13-023 | Crockett | IH 10 | Construct Rest Area | 6 | RAGLE CONSTRUCTION, INC. | $13,741,321 | $19,998,295 | 68.7% |
| 2026-08-06 | 0069-07-113 | Tom Green | US 87 | Intersection Improvement | 2 | REECE ALBERT, INC. | $2,825,728 | $1,800,040 | 157.0% |
| 2026-08-05 | 0907-00-239 | Tom Green | AVE N | Install Traffic Signal | 3 | E-Z BEL CONSTRUCTION, LLC | $589,192 | $579,255 | 101.7% |
| 2026-07-28 | 6499-27-001 | Real | US0083 | MOWING HIGHWAY RIGHT OF WAY | 2 | R&M INCORPORATED | $348,532 | $290,431 | 120.0% |
| 2026-07-23 | 6488-50-001 | Reagan | US0067 | MOWING HIGHWAY RIGHT OF WAY | 4 | LUKEDA SANDBLASTING & SERVICES LLC | $183,407 | $193,459 | 94.8% |
| 2026-07-23 | 6485-05-001 | Coke | SH0158 | MOWING HIGHWAY RIGHT OF WAY | 5 | BOEN LANDSCAPING & IRRIGATION, LLC | $167,400 | $166,686 | 100.4% |
| 2026-07-16 | 6499-24-001 | Sterling | US0087 | MOWING HIGHWAY RIGHT OF WAY | 4 | DESERT LUXURY TRANSPORTATION, LLC | $237,103 | $227,949 | 104.0% |
| 2026-07-16 | 6499-22-001 | Concho | US0087 | MOWING HIGHWAY RIGHT OF WAY | 3 | TRIPLE T MAINTENANCE INC. | $270,356 | $266,010 | 101.6% |
| 2026-07-09 | 6499-26-001 | Runnels | FM2887 | MOWING HIGHWAY RIGHT OF WAY | 5 | R&M INCORPORATED | $204,319 | $194,600 | 105.0% |
| 2026-07-09 | 6499-25-001 | Kimble | US0377 | MOWING HIGHWAY RIGHT OF WAY | 3 | R&M INCORPORATED | $237,736 | $209,489 | 113.5% |
| 2026-07-01 | 0070-03-062 | Concho | US 87 | Hazard Elimination & Safety | 5 | MASSANA CONSTRUCTION INC. | $2,660,738 | $3,774,746 | 70.5% |
| 2026-06-18 | 6503-69-001 | Tom Green | US0087 | FLEXIBLE BASE | 3 | TOUCHSTONE RESOURCES, LLC | $83,550 | $98,337 | 85.0% |
| 2026-06-02 | 0907-00-236 | Tom Green | Various | Bicycle And Pedestrian Improvements | 7 | TI-ZACK CONCRETE, LLC | $1,672,395 | $2,079,597 | 80.4% |
| 2026-06-02 | 0907-00-235 | Tom Green | Various | Bridge Maintenance | 9 | MACIAS SPECIALTY CONTRACTING LLC | $306,395 | $418,763 | 73.2% |
| 2026-05-28 | 6501-03-001 | Tom Green | SH0208 | METAL BEAM GUARD FENCE REPAIR | 4 | AUSTIN BARRICADE COMPANY, L.L.C. | $427,879 | $508,475 | 84.1% |
| 2026-05-06 | 0077-07-010 | Irion | FM 72 | Bridge Replacement | 10 | DELGADO'S CONTRACTORS, LLC | $4,405,521 | $5,202,797 | 84.7% |
| 2026-05-05 | 6477-64-001 | Tom Green | SH0208 | RAISED PAVEMENT MARKERS | 7 | ANTHONY SERVICES | $449,501 | $686,415 | 65.5% |
| 2026-04-16 | 6487-86-001 | Tom Green | RM0584 | REHABILITATION OF EXISTING ROADWAY | 2 | O. TREVINO CONSTRUCTION, LLC | $762,302 | $588,345 | 129.6% |
| 2026-04-16 | 6474-39-001 | Kimble | US0377 | METAL BEAM GUARD FENCE REPAIR | 4 | T&L CLEANING SERVICES LLC | $403,154 | $523,020 | 77.1% |
| 2026-04-09 | 6500-10-001 | Sutton | US0277 | EMULSION | 2 | MARTIN RESOURCE MANAGEMENT CORPORATION | $38,988 | $44,916 | 86.8% |
| 2026-03-26 | 6481-65-001 | Kimble | US0377 | PAVEMENT MARKINGS | 5 | L&L COMPANY | $199,196 | $326,465 | 61.0% |
| 2026-03-24 | 6498-45-001 | Reagan | US0067 | EMULSION | 2 | ERGON ASPHALT & EMULSIONS, INC. | $514,140 | $560,481 | 91.7% |
| 2026-03-24 | 6498-44-001 | Runnels | US0067 | LIMESTONE ROCK ASPHALT | 2 | VULCAN CONSTRUCTION MATERIALS, LLC | $558,123 | $602,323 | 92.7% |
| 2026-03-24 | 6480-65-001 | Tom Green | SH0208 | PAVEMENT MARKINGS | 6 | FLAT LINE, INC. | $77,856 | $128,450 | 60.6% |
| 2026-03-04 | 0034-05-042 | Coke, Concho, Crockett, Reagan, Runnels | US 67 | Preventive Maintenance | 3 | RK HALL, LLC | $10,981,878 | $14,058,843 | 78.1% |
| 2026-02-05 | 0077-01-032 | Reagan | US 67 | Traffic Signal Improvements | 4 | E-Z BEL CONSTRUCTION, LLC | $512,494 | $512,766 | 99.9% |
| 2026-01-15 | 6493-76-001 | Kimble | US0377 | BRIDGE PREVENTATIVE MAINTENANCE | 10 | MPB, INC. | $365,527 | $543,207 | 67.3% |
| 2026-01-01 | 6490-17-001 | Tom Green | SH0208 | STATE USE CONTRACT | 0 | – | – | $34,397 | – |
| 2026-01-01 | 6490-09-001 | Tom Green | RM0584 | STATE USE CONTRACT | 0 | – | – | $82,121 | – |
| 2025-12-09 | 6494-78-001 | Tom Green | SH0208 | MOWING HIGHWAY RIGHT OF WAY | 1 | ABESCAPE GROUP LLC | $184,808 | $187,200 | 98.7% |
| 2025-12-09 | 6477-62-001 | Kimble | IH0010 | DEBRIS REMOVAL | 2 | SUNDROP GARDENS LANDSCAPING, LLC | $350,081 | $378,435 | 92.5% |
| 2025-12-02 | 0077-06-105 | Coke, Crockett, Edwards, Kimble, Menard, Real, Runnels, Schleicher, Sterling, Sutton, Tom Green | US 67 | Seal Coat | 2 | RONALD R. WAGNER & CO., LP | $11,201,011 | $13,517,648 | 82.9% |
| 2025-11-20 | 6486-28-001 | Tom Green | SH0208 | BRIDGE PREVENTATIVE MAINTENANCE | 11 | BK FIELD OPERATIONS LLC | $505,934 | $750,055 | 67.5% |
| 2025-11-19 | 6493-30-001 | Runnels | US0067 | AGGREGATE | 3 | MARTIN MARIETTA MATERIALS, INC. | $211,194 | $223,000 | 94.7% |
| 2025-11-19 | 6493-29-001 | Concho | US0083 | Sand | 1 | TOUCHSTONE RESOURCES, LLC | $116,000 | $115,596 | 100.3% |
| 2025-11-19 | 6493-28-001 | Runnels | US0067 | Sand | 1 | TOUCHSTONE RESOURCES, LLC | $111,000 | $131,150 | 84.6% |
| 2025-10-14 | 6483-70-001 | Tom Green | SH0208 | CRACK SEAL | 1 | D & M CONTRACTORS, LLC | $828,114 | $758,795 | 109.1% |
| 2025-10-09 | 0907-00-216 | Tom Green | Various | Highway Improvement | 9 | L&L COMPANY | $2,488,408 | $2,956,233 | 84.2% |
| 2025-10-02 | 6486-06-001 | Tom Green | SH0208 | MOWING HIGHWAY RIGHT OF WAY | 6 | YANACEK IRRIGATION | $186,000 | $187,200 | 99.4% |
| 2025-09-19 | 6489-03-001 | Tom Green | US 67 | EMERGENCY CULVERT REPAIR/REPLACEMENT | 0 | – | – | $11,781,879 | – |
| 2025-09-18 | 6490-35-001 | Tom Green | US0067 | WINTER WEATHER MATERIAL | 2 | TOUCHSTONE RESOURCES, LLC | $79,200 | $71,516 | 110.7% |
| 2025-09-18 | 6490-34-001 | Tom Green | US0087 | WINTER WEATHER MATERIAL | 2 | NSG LOGISTICS, LLC | $631,352 | $586,035 | 107.7% |
| 2025-09-05 | 0069-02-035 | Glasscock, Runnels, Tom Green | US 87 | Bridge Maintenance | 8 | RAGLE CONSTRUCTION, INC. | $2,242,482 | $3,031,421 | 74.0% |
"Apparent low bidder" is rank 1 as read at the letting. It is not a record of award; TxDOT can reject bids. Bidders are businesses that bid on public contracts.
Source: TxDOT Bid Tabulations, retrieved 2026-11-26. Full list as JSON: /api/v1/tx/districts/san-angelo.json