TxDOT item 346-7009: STONE-MTRX-ASPH SMA-D SAC-A PG76-22
Unit: TON. Apparent low-bid unit prices for this item across 61 TxDOT lettings from 2024-11-06 to 2026-11-04.
8 row(s) with quantity of zero or less were left out of these statistics.
Last 24 months
61Low bids
$164.00Median
$135.8725th pct
$200.0075th pct
$152.44Qty-weighted avg
$105.75 / $383.00Min / max
$150.00Engineer's est. median
102.5%Low ÷ estimate (median)
Last 12 months
30Low bids
$153.98Median
$135.9025th pct
$192.9475th pct
$148.79Qty-weighted avg
$115.00 / $244.75Min / max
$150.00Engineer's est. median
102.9%Low ÷ estimate (median)
Median by TxDOT district
| District | Low bids | Median unit price |
|---|---|---|
| Odessa | 20 | $132.00 |
| Pharr | 13 | $135.30 |
| Beaumont | 8 | $211.00 |
| Austin | 4 | $195.00 |
| Abilene | 3 | $164.50 |
| Waco | 3 | $130.00 |
| Dallas | 3 | $165.00 |
| Houston | 3 | $188.75 |
| Tyler | 3 | $186.75 |
| Bryan | 2 | $174.50 |
| San Antonio | 2 | $123.00 |
| El Paso | 1 | $151.15 |
| Yoakum | 1 | $161.70 |
| Brownwood | 1 | $286.00 |
| Atlanta | 1 | $225.00 |
| Corpus Christi | 1 | $172.00 |
Most recent low bids
| Let date | CCSJ | County | District | Qty | Low unit price | Engineer's est. |
|---|---|---|---|---|---|---|
| 2026-11-04 | 0157-04-058 | Haskell | Abilene | 2.13e+04 | $164.50 | $160.00 |
| 2026-11-03 | 0220-01-038 | Hidalgo | Pharr | 4.81e+04 | $135.30 | $140.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 3.81e+03 | $207.19 | $188.75 |
| 2026-10-07 | 0014-23-041 | Hill | Waco | 5.76e+04 | $130.00 | $140.00 |
| 2026-09-02 | 3632-01-002 | Starr | Pharr | 2.47e+04 | $134.00 | $140.00 |
| 2026-08-05 | 0441-09-054 | Reeves | Odessa | 0 | $0.00 | $125.00 |
| 2026-08-05 | 0114-02-112 | Travis | Austin | 1.09e+04 | $195.00 | $155.00 |
| 2026-07-02 | 0508-02-140 | Chambers | Beaumont | 6.24e+03 | $217.00 | $160.00 |
| 2026-07-02 | 0005-04-084 | Martin | Odessa | 2.85e+03 | $220.00 | $130.00 |
| 2026-07-01 | 1194-02-020 | Hardin | Beaumont | 1.45e+04 | $220.00 | $150.00 |
| 2026-07-01 | 0229-01-042 | Ector | Odessa | 1.62e+04 | $142.00 | $138.00 |
| 2026-06-03 | 0337-01-053 | Williamson | Austin | 2.79e+03 | $195.00 | $180.00 |
| 2026-06-03 | 0065-08-173 | Jefferson | Beaumont | 6.85e+03 | $244.75 | $210.00 |
| 2026-05-07 | 6498-15-001 | Denton | Dallas | 2.32e+04 | $136.00 | $163.67 |
| 2026-05-07 | 6488-81-001 | Robertson | Bryan | 1.29e+04 | $149.00 | $170.00 |
| 2026-05-07 | 0255-06-073 | Hidalgo | Pharr | 2.56e+04 | $142.00 | $130.00 |
| 2026-04-08 | 1823-01-011 | Martin | Odessa | 1.05e+04 | $144.00 | $140.00 |
| 2026-04-08 | 0005-08-109 | Mitchell | Abilene | 3.02e+04 | $160.00 | $136.65 |
| 2026-04-07 | 6470-82-001 | Cameron | Pharr | 9.88e+03 | $155.96 | $122.10 |
| 2026-04-07 | 0255-07-153 | Hidalgo | Pharr | 2.58e+04 | $135.87 | $135.54 |
Quantities matter: small quantities often carry higher unit prices. Lump-sum (LS) items are whole-job amounts. Compare projects of similar size before using a number.
Source: TxDOT Bid Tabulations, bid code 346-7009 on the Texas Open Data Portal, retrieved 2026-11-26. JSON: /api/v1/tx/items/346-7009.json