TxDOT item 432-7013: RIPRAP (MOW STRIP)(4 IN)
Unit: CY. Apparent low-bid unit prices for this item across 589 TxDOT lettings from 2024-11-06 to 2026-11-12.
Last 24 months
593Low bids
$670.00Median
$583.9025th pct
$775.0075th pct
$616.83Qty-weighted avg
$1.00 / $3,900.00Min / max
$675.00Engineer's est. median
100.0%Low ÷ estimate (median)
Last 12 months
307Low bids
$650.00Median
$566.0025th pct
$750.0075th pct
$590.45Qty-weighted avg
$1.00 / $3,900.00Min / max
$650.00Engineer's est. median
98.2%Low ÷ estimate (median)
Median by TxDOT district
| District | Low bids | Median unit price |
|---|---|---|
| Dallas | 71 | $700.00 |
| Houston | 56 | $738.35 |
| San Antonio | 43 | $646.88 |
| Fort Worth | 42 | $707.50 |
| Austin | 35 | $650.00 |
| Beaumont | 33 | $700.00 |
| Bryan | 31 | $600.00 |
| Tyler | 28 | $650.00 |
| Paris | 27 | $650.00 |
| Pharr | 27 | $600.00 |
| Atlanta | 24 | $532.50 |
| Waco | 22 | $690.00 |
| Laredo | 20 | $624.02 |
| Wichita Falls | 17 | $750.00 |
| Odessa | 16 | $785.00 |
| Corpus Christi | 16 | $603.00 |
| Childress | 15 | $800.00 |
| Amarillo | 14 | $701.50 |
| Abilene | 13 | $715.00 |
| San Angelo | 12 | $697.71 |
| Brownwood | 10 | $644.50 |
| El Paso | 8 | $625.00 |
| Lufkin | 8 | $365.00 |
| Yoakum | 5 | $650.00 |
Most recent low bids
| Let date | CCSJ | County | District | Qty | Low unit price | Engineer's est. |
|---|---|---|---|---|---|---|
| 2026-11-12 | 6497-55-001 | Denton | Dallas | 3 | $700.00 | $650.00 |
| 2026-11-04 | 1017-03-040 | Hunt | Paris | 70 | $600.00 | $500.00 |
| 2026-11-04 | 0947-03-034 | Jasper | Beaumont | 108 | $660.00 | $635.00 |
| 2026-11-04 | 0922-33-234 | Webb | Laredo | 44 | $623.05 | $695.00 |
| 2026-11-04 | 0212-03-058 | Brazos | Bryan | 100 | $675.00 | $700.00 |
| 2026-11-04 | 0195-02-092 | Denton | Dallas | 478 | $465.00 | $625.00 |
| 2026-11-04 | 0157-04-058 | Haskell | Abilene | 107 | $765.00 | $800.00 |
| 2026-11-03 | 0917-30-068 | Burleson | Bryan | 37 | $500.00 | $750.00 |
| 2026-11-03 | 0220-01-038 | Hidalgo | Pharr | 153 | $429.43 | $565.00 |
| 2026-11-03 | 0038-01-107 | Webb | Laredo | 1.36e+03 | $425.00 | $500.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 43 | $643.09 | $600.00 |
| 2026-10-15 | 6503-97-001 | McLennan | Waco | 6 | $800.00 | $1,062.60 |
| 2026-10-07 | 6503-84-001 | McLennan | Waco | 75 | $300.00 | $700.00 |
| 2026-10-07 | 1137-02-044 | Cameron | Pharr | 8 | $750.00 | $590.00 |
| 2026-10-07 | 0922-20-030 | La Salle | Laredo | 30 | $588.00 | $700.00 |
| 2026-10-07 | 0510-06-024 | Fannin | Paris | 669 | $650.00 | $570.00 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 73 | $676.65 | $675.00 |
| 2026-10-07 | 0092-03-064 | Ellis | Dallas | 2 | $1,062.00 | $675.00 |
| 2026-10-07 | 0092-02-145 | Dallas | Dallas | 235 | $828.81 | $725.00 |
| 2026-10-07 | 0022-01-034 | Terrell | Odessa | 58 | $675.00 | $700.00 |
Quantities matter: small quantities often carry higher unit prices. Lump-sum (LS) items are whole-job amounts. Compare projects of similar size before using a number.
Source: TxDOT Bid Tabulations, bid code 432-7013 on the Texas Open Data Portal, retrieved 2026-11-26. JSON: /api/v1/tx/items/432-7013.json