TxDOT item 462-7003: CONC BOX CULV (4 FT X 2 FT)
Unit: LF. Apparent low-bid unit prices for this item across 46 TxDOT lettings from 2025-01-07 to 2026-11-04.
Last 24 months
46Low bids
$400.00Median
$331.2525th pct
$550.0075th pct
$419.86Qty-weighted avg
$250.00 / $1,450.00Min / max
$450.00Engineer's est. median
89.1%Low ÷ estimate (median)
Last 12 months
25Low bids
$360.00Median
$322.0025th pct
$550.0075th pct
$427.78Qty-weighted avg
$257.60 / $1,450.00Min / max
$425.00Engineer's est. median
79.0%Low ÷ estimate (median)
Median by TxDOT district
| District | Low bids | Median unit price |
|---|---|---|
| San Antonio | 9 | $360.00 |
| Dallas | 7 | $400.00 |
| Odessa | 4 | $411.00 |
| Austin | 3 | $640.11 |
| Abilene | 3 | $550.00 |
| Houston | 2 | $259.88 |
| Fort Worth | 2 | $332.50 |
| Yoakum | 2 | $518.50 |
| Waco | 2 | $374.23 |
| Amarillo | 2 | $487.50 |
| Brownwood | 1 | $716.03 |
| Laredo | 1 | $341.40 |
| Atlanta | 1 | $322.00 |
| Childress | 1 | $759.00 |
| Tyler | 1 | $250.00 |
| El Paso | 1 | $450.00 |
| Bryan | 1 | $400.00 |
| Lufkin | 1 | $990.00 |
| Paris | 1 | $380.00 |
| Pharr | 1 | $390.00 |
Most recent low bids
| Let date | CCSJ | County | District | Qty | Low unit price | Engineer's est. |
|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 1.25e+03 | $325.00 | $360.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 1.68e+03 | $686.01 | $450.00 |
| 2026-08-06 | 3510-04-069 | Fort Bend | Houston | 86 | $262.15 | $440.00 |
| 2026-08-06 | 2528-01-006 | Reeves | Odessa | 308 | $415.00 | $425.00 |
| 2026-08-05 | 0027-08-147 | Fort Bend | Houston | 840 | $257.60 | $350.00 |
| 2026-08-05 | 0014-15-034 | Tarrant | Fort Worth | 2.24e+03 | $335.00 | $380.00 |
| 2026-07-01 | 0229-01-042 | Ector | Odessa | 1.14e+03 | $671.88 | $360.00 |
| 2026-07-01 | 0014-03-088 | Johnson | Fort Worth | 84 | $330.00 | $425.00 |
| 2026-06-03 | 0923-08-042 | Coleman | Brownwood | 14 | $716.03 | $750.00 |
| 2026-06-03 | 0366-02-089 | Guadalupe | San Antonio | 98 | $310.00 | $475.00 |
| 2026-06-03 | 0291-03-077 | Kerr | San Antonio | 548 | $292.64 | $400.00 |
| 2026-05-07 | 1269-01-023 | Guadalupe | San Antonio | 150 | $455.63 | $350.00 |
| 2026-04-08 | 2230-01-020 | Bexar | San Antonio | 247 | $310.70 | $408.00 |
| 2026-04-08 | 0197-02-138 | Dallas | Dallas | 8 | $1,450.00 | $350.00 |
| 2026-04-07 | 0299-14-010 | Maverick | Laredo | 535 | $341.40 | $450.00 |
| 2026-04-07 | 0269-10-028 | Lavaca | Yoakum | 33 | $672.00 | $270.00 |
| 2026-03-04 | 0581-02-156 | Dallas | Dallas | 435 | $550.00 | $350.00 |
| 2026-03-04 | 0046-03-040 | Bowie | Atlanta | 310 | $322.00 | $445.00 |
| 2026-02-04 | 1015-01-024 | Rockwall | Dallas | 1.32e+03 | $400.00 | $360.00 |
| 2026-01-07 | 0975-02-023 | Jones | Abilene | 72 | $550.00 | $900.00 |
Quantities matter: small quantities often carry higher unit prices. Lump-sum (LS) items are whole-job amounts. Compare projects of similar size before using a number.
Source: TxDOT Bid Tabulations, bid code 462-7003 on the Texas Open Data Portal, retrieved 2026-11-26. JSON: /api/v1/tx/items/462-7003.json