TxDOT item 465-7014: INLET (COMPL)(PCO)(3FT)(LEFT)
Unit: EA. Apparent low-bid unit prices for this item across 29 TxDOT lettings from 2025-01-08 to 2026-11-04.
Last 24 months
29Low bids
$7,250.00Median
$5,500.0025th pct
$8,000.4575th pct
$8,573.78Qty-weighted avg
$3,931.24 / $15,471.00Min / max
$7,500.00Engineer's est. median
92.9%Low ÷ estimate (median)
Last 12 months
17Low bids
$7,250.00Median
$5,500.0025th pct
$8,378.3575th pct
$9,017.41Qty-weighted avg
$4,800.00 / $15,471.00Min / max
$7,500.00Engineer's est. median
94.6%Low ÷ estimate (median)
Median by TxDOT district
| District | Low bids | Median unit price |
|---|---|---|
| San Antonio | 7 | $8,378.35 |
| Austin | 6 | $6,875.00 |
| Pharr | 5 | $5,500.00 |
| Dallas | 3 | $7,721.32 |
| Abilene | 2 | $7,091.05 |
| Corpus Christi | 2 | $6,100.00 |
| Houston | 1 | $7,357.90 |
| Lubbock | 1 | $14,580.00 |
| Waco | 1 | $8,000.45 |
| Amarillo | 1 | $10,650.00 |
Most recent low bids
| Let date | CCSJ | County | District | Qty | Low unit price | Engineer's est. |
|---|---|---|---|---|---|---|
| 2026-11-04 | 0047-04-032 | Collin | Dallas | 34 | $11,125.00 | $8,500.00 |
| 2026-11-03 | 0015-13-432 | Travis | Austin | 20 | $7,700.00 | $5,500.00 |
| 2026-09-02 | 3632-01-002 | Starr | Pharr | 2 | $5,500.00 | $6,000.00 |
| 2026-08-05 | 0027-08-147 | Fort Bend | Houston | 3 | $7,357.90 | $6,500.00 |
| 2026-07-02 | 1502-01-031 | Lubbock | Lubbock | 38 | $14,580.00 | $6,000.00 |
| 2026-07-02 | 0921-00-091 | Hidalgo | Pharr | 1 | $5,500.00 | $7,000.00 |
| 2026-07-01 | 2452-03-128 | Bexar | San Antonio | 1 | $8,378.35 | $7,800.00 |
| 2026-06-03 | 0366-02-089 | Guadalupe | San Antonio | 1 | $10,000.00 | $6,200.00 |
| 2026-06-03 | 0337-01-053 | Williamson | Austin | 2 | $7,250.00 | $7,800.00 |
| 2026-06-03 | 0006-06-109 | Taylor | Abilene | 10 | $7,000.00 | $7,600.00 |
| 2026-05-07 | 0521-04-285 | Bexar | San Antonio | 1 | $7,865.44 | $9,000.00 |
| 2026-05-06 | 2094-01-063 | Hidalgo | Pharr | 18 | $5,500.00 | $4,773.00 |
| 2026-05-06 | 0073-08-183 | Bexar | San Antonio | 4 | $5,083.10 | $7,500.00 |
| 2026-04-08 | 2230-01-020 | Bexar | San Antonio | 45 | $6,392.80 | $9,000.00 |
| 2026-04-07 | 2452-01-066 | Bexar | San Antonio | 2 | $15,471.00 | $8,000.00 |
| 2026-02-05 | 1201-02-026 | Williamson | Austin | 1 | $6,150.00 | $6,500.00 |
| 2026-01-06 | 0989-02-057 | Nueces | Corpus Christi | 7 | $4,800.00 | $7,500.00 |
| 2025-11-06 | 0113-13-168 | Travis | Austin | 2 | $7,675.00 | $8,500.00 |
| 2025-11-05 | 0231-19-003 | Coryell | Waco | 1 | $8,000.45 | $7,000.00 |
| 2025-10-08 | 0034-01-130 | Taylor | Abilene | 4 | $7,182.09 | $7,000.00 |
Quantities matter: small quantities often carry higher unit prices. Lump-sum (LS) items are whole-job amounts. Compare projects of similar size before using a number.
Source: TxDOT Bid Tabulations, bid code 465-7014 on the Texas Open Data Portal, retrieved 2026-11-26. JSON: /api/v1/tx/items/465-7014.json