TxDOT item 465-7162: INLET(COMPL)(PAZD)(FG)(5FTX5FT-4FTX4FT)
Unit: EA. Apparent low-bid unit prices for this item across 16 TxDOT lettings from 2024-12-03 to 2026-07-02.
Last 24 months
16Low bids
$8,900.00Median
$7,140.0025th pct
$10,152.5075th pct
$9,667.00Qty-weighted avg
$6,100.00 / $16,783.55Min / max
$10,375.00Engineer's est. median
87.6%Low ÷ estimate (median)
Last 12 months
8Low bids
$10,050.00Median
$8,017.5025th pct
$10,394.5775th pct
$10,618.58Qty-weighted avg
$6,500.00 / $16,783.55Min / max
$10,750.00Engineer's est. median
98.1%Low ÷ estimate (median)
Median by TxDOT district
| District | Low bids | Median unit price |
|---|---|---|
| Dallas | 3 | $7,320.00 |
| Austin | 3 | $8,250.00 |
| San Antonio | 2 | $10,374.14 |
| Tyler | 1 | $10,310.00 |
| Abilene | 1 | $6,500.00 |
| Fort Worth | 1 | $10,000.00 |
| Laredo | 1 | $16,783.55 |
| Waco | 1 | $8,800.00 |
| Pharr | 1 | $6,100.00 |
| Bryan | 1 | $8,800.00 |
| Corpus Christi | 1 | $9,600.00 |
Most recent low bids
| Let date | CCSJ | County | District | Qty | Low unit price | Engineer's est. |
|---|---|---|---|---|---|---|
| 2026-07-02 | 0492-04-034 | Smith | Tyler | 1 | $10,310.00 | $8,000.00 |
| 2026-07-01 | 2452-03-128 | Bexar | San Antonio | 2 | $10,648.28 | $15,300.00 |
| 2026-07-01 | 0016-05-128 | Comal | San Antonio | 3 | $10,100.00 | $10,500.00 |
| 2026-06-03 | 0006-06-109 | Taylor | Abilene | 1 | $6,500.00 | $11,500.00 |
| 2026-06-02 | 1179-02-041 | Parker | Fort Worth | 2 | $10,000.00 | $10,000.00 |
| 2026-05-06 | 0081-03-047 | Denton | Dallas | 2 | $7,320.00 | $25,000.00 |
| 2026-04-07 | 0299-14-010 | Maverick | Laredo | 3 | $16,783.55 | $11,000.00 |
| 2026-02-05 | 1201-02-026 | Williamson | Austin | 2 | $8,250.00 | $7,500.00 |
| 2025-11-06 | 0113-13-168 | Travis | Austin | 1 | $12,512.38 | $13,000.00 |
| 2025-09-04 | 3623-01-004 | Coryell | Waco | 1 | $8,800.00 | $11,500.00 |
| 2025-09-04 | 0918-46-300 | Denton | Dallas | 1 | $9,000.00 | $6,600.00 |
| 2025-08-08 | 0323-01-028 | Bastrop | Austin | 2 | $6,150.14 | $10,250.00 |
| 2025-08-07 | 0921-06-342 | Cameron | Pharr | 1 | $6,100.00 | $9,775.00 |
| 2025-08-07 | 0540-03-037 | Brazos | Bryan | 3 | $8,800.00 | $10,000.00 |
| 2025-07-01 | 0327-09-002 | Kleberg | Corpus Christi | 4 | $9,600.00 | $11,000.00 |
| 2024-12-03 | 0047-05-057 | Collin | Dallas | 1 | $6,600.00 | $10,000.00 |
Quantities matter: small quantities often carry higher unit prices. Lump-sum (LS) items are whole-job amounts. Compare projects of similar size before using a number.
Source: TxDOT Bid Tabulations, bid code 465-7162 on the Texas Open Data Portal, retrieved 2026-11-26. JSON: /api/v1/tx/items/465-7162.json