TxDOT item 684-7009: TRF SIG CBL (TY A)(12 AWG)(4 CONDR)
Unit: LF. Apparent low-bid unit prices for this item across 56 TxDOT lettings from 2024-11-06 to 2026-11-03.
Last 24 months
56Low bids
$3.00Median
$2.4825th pct
$3.1275th pct
$2.79Qty-weighted avg
$1.00 / $5.50Min / max
$2.67Engineer's est. median
109.5%Low ÷ estimate (median)
Last 12 months
30Low bids
$3.00Median
$2.7125th pct
$3.2975th pct
$2.87Qty-weighted avg
$1.50 / $5.25Min / max
$2.74Engineer's est. median
107.7%Low ÷ estimate (median)
Median by TxDOT district
| District | Low bids | Median unit price |
|---|---|---|
| San Antonio | 17 | $3.00 |
| Houston | 15 | $3.00 |
| Laredo | 5 | $2.50 |
| Beaumont | 4 | $2.76 |
| Pharr | 3 | $1.50 |
| Tyler | 2 | $3.23 |
| Austin | 2 | $1.88 |
| Odessa | 2 | $5.38 |
| Atlanta | 2 | $3.00 |
| Lubbock | 1 | $3.50 |
| Fort Worth | 1 | $3.25 |
| Abilene | 1 | $3.00 |
| Corpus Christi | 1 | $2.00 |
Most recent low bids
| Let date | CCSJ | County | District | Qty | Low unit price | Engineer's est. |
|---|---|---|---|---|---|---|
| 2026-11-03 | 6504-89-001 | Harris | Houston | 3e+04 | $3.09 | $2.50 |
| 2026-10-07 | 0143-03-049 | Wilson | San Antonio | 2.48e+03 | $2.20 | $2.89 |
| 2026-09-03 | 1801-01-064 | Cameron | Pharr | 1.74e+03 | $1.50 | $2.84 |
| 2026-09-03 | 1479-01-028 | Bexar | San Antonio | 670 | $4.16 | $2.72 |
| 2026-08-06 | 0018-05-089 | Webb | Laredo | 6.24e+03 | $1.95 | $2.00 |
| 2026-08-05 | 0027-08-147 | Fort Bend | Houston | 635 | $3.10 | $2.00 |
| 2026-07-01 | 2452-03-128 | Bexar | San Antonio | 5.33e+03 | $2.85 | $2.67 |
| 2026-07-01 | 0905-06-121 | Lubbock | Lubbock | 40 | $3.50 | $5.30 |
| 2026-07-01 | 0712-01-052 | Johnson | Fort Worth | 185 | $3.25 | $3.00 |
| 2026-07-01 | 0165-02-061 | Smith | Tyler | 1.6e+03 | $3.60 | $2.85 |
| 2026-06-03 | 0921-02-534 | Hidalgo | Pharr | 1.45e+03 | $3.00 | $1.00 |
| 2026-06-03 | 0720-03-153 | Harris | Houston | 1.19e+04 | $3.00 | $2.80 |
| 2026-06-03 | 0366-02-089 | Guadalupe | San Antonio | 6.54e+03 | $3.30 | $2.75 |
| 2026-06-03 | 0291-03-077 | Kerr | San Antonio | 171 | $3.20 | $3.00 |
| 2026-06-03 | 0073-03-071 | Atascosa | San Antonio | 2.13e+03 | $4.00 | $3.50 |
| 2026-06-03 | 0006-06-109 | Taylor | Abilene | 6.18e+03 | $3.00 | $3.00 |
| 2026-05-07 | 0521-04-285 | Bexar | San Antonio | 2.26e+03 | $2.65 | $2.65 |
| 2026-05-06 | 0915-00-280 | Bexar | San Antonio | 2e+03 | $3.00 | $2.00 |
| 2026-05-06 | 0389-02-059 | Chambers | Beaumont | 3.38e+03 | $3.20 | $3.00 |
| 2026-04-08 | 2230-01-020 | Bexar | San Antonio | 4.93e+03 | $2.70 | $2.75 |
Quantities matter: small quantities often carry higher unit prices. Lump-sum (LS) items are whole-job amounts. Compare projects of similar size before using a number.
Source: TxDOT Bid Tabulations, bid code 684-7009 on the Texas Open Data Portal, retrieved 2026-11-26. JSON: /api/v1/tx/items/684-7009.json